Memorabilia

    1.December 2013, started construction
       2013年12月,工程启动建设。

    2.10th January,2014, start the construction of the 1st phase cofferdam and the diversion channel on the left bank
       
2014年1月10日,一期土石围堰及左岸导流明渠开始施工。
    3.
1st December 2014, started filling the earth dams on both left and right banks
       
2014年12月1日,启动左右岸土坝填筑施工。
    4.18th December 2014, diversion channel start to diverting the river
       
2014年12月28日,导流明渠过流。
    5.7th January 2015, closed the mainstream of the river
       
2015年1月7日,主河床成功截流。
    6.
20th April 2015, completed the excavation of foundation pit on the main river bed
       
2015年4月20日,主河床基坑开挖完成。
    7.31st May 2015, completed the filling of the 2nd phase upstream and downstream cofferdams
       
2015年5月31日,二期上下游围堰填筑完成。
    8.June 2016, concreting work for the spillway section entirely  reached the designed top elevation
       
2016年6月,泄洪坝段全线浇筑到顶。
    9.October 2016, concreting work for the powerhouse intake section entirely reached the designed top elevation
        2016年10月,厂房进水口全线浇筑到顶。
    10.10th January 2017, completed the installation and commissioning tests for the gates at spillway, intake and draft tube of the powerhouse
       
2017年1月10日,泄洪坝段、厂房进尾水坝段闸门安装调试完成。
    11.20th January 2017, closed the diversion channel(the 3rd phase closure)
       2017年1月20日,实现三期截流。