Earth filled dam in diversion channel section started

      6 February 2017, the earth filled dam in diversion channel started to fill, which advanced 23 days comparing to original plan.
      2月6日,桑河二级水电站导流明渠段土坝开始填筑,比原定计划提前23天。
     
The company will continuously enhance the site producing organization to fill the earth dam in whole section in a short time, ensure the dam at this section can be filled to the designed top elevation before the rainy season, and create further favorable conditions for the gate closure, reservoir filling and the achievement of the target of the timely operation of the 1st Unit.
     
桑河公司将继续加强现场生产组织,尽快形成全断面土坝填筑的态势,确保汛前坝体填筑到顶,为后续下闸蓄水及首机发电目标实现创造更为有利的条件。