The Hydro Power Lower Sesan 2 Station Successfully Completed the Overhaul of the First Turbine Unit after Commercial Operation Date

At 19:00 on May 18th, Unit No.4 of the Hydro Power Lower Sesan 2 Station was handed over to the dispatch in advance, it means that the first round of repair work after the commercial operation of the power station has been successfully completed.
           5月1819:00,桑河二级水电站4号机组提前移交调度,标志着电站商业运行后首轮机组检修工作圆满结束。

The maintenance lasted for 79 days and mainly consisted of 5 units of C-level maintenance. A total of 640 standard items were completed and 113 special items were treated.
          本次检修历时79天,主要包括5台机组C级检修,累计完成标准项目640项,专项处理项目113项。