The Hydro Power Lower Sesan 2 Station Has Officially Entered Commercial Operation

Personally announced by the Prime Minister of the Kingdom of Cambodia, Hun Sen, at the completion ceremony and confirmed by the Electricité du Cambodge Company, the Hydro Power Lower Sesan 2 Station (the”Hydropower Station”) has officially entered commercial operation at 10:30 a.m. on December 17th, 2018.
         
由柬埔寨王国首相洪森在电站竣工仪式上亲自宣布,经柬埔寨国家电力公司正式发函确认,桑河二级水电站于2018121710:30正式进入商业运行。

The total installed capacity of the Hydropower Station is 400,000 kilowatts. It adopts 8 sets of 50,000-kilowatt bulb tubular-flow units and the average annual power generation is 1.97 billion kWh. The BOT mode (construction-operation-transfer) is adopted during the development of the Hydropower Station. The construction period is 5 years and will be handed over to the Cambodian government 40 years after commercial operation.
        
桑河二级水电站共安装8台单机容量5万千瓦灯泡贯流式机组,总装机容量40万千瓦,年平均发电量19.7亿千瓦时。电站采用BOT模式(建设--运营--移交)开发,建设期5年,商业运行40年后移交柬埔寨政府。